Posted Monday, June 12, 2017

Waterloo Region – GrandLinq has informed the Region that final asphalt paving operations on Caroline (Erb to Allen) and Allen (Caroline to King) in UpTown Waterloo have been postponed. The work, which was set to start yesterday (June 11), will be re-scheduled at a later date.
 
Final asphalt paving is postponed due to anomalies found on Saturday (June 10) during final testing related to cathodic protection. Cathodic protection significantly reduces rusting...

Read More...

Posted Thursday, June 08, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that they have re-scheduled final asphalt paving operations on Caroline and Allen in UpTown Waterloo, June 11-13. The work, which was originally scheduled for June 6-7, was postponed earlier this week due to weather. 
 
To minimize the impact on area businesses and residents, the work will be completed at night (7 p.m. to 7 a.m.), with access reinstated during the day. A full closure of...

Read More...

Posted Tuesday, June 06, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that due to the rain expected today, they will need to make adjustments to their final asphalt paving schedule in UpTown Waterloo.
 
The weather delay means that final asphalt paving on Caroline (Erb to Allen) and Allen (Caroline to King) originally scheduled to take place today (June 6) and Wednesday (June 7) will not occur this week. A new schedule for this work will be announced once arrangements...

Read More...

Posted Wednesday, May 31, 2017

Waterloo Region –  GrandLinq has advised the Region of Waterloo that they will complete final asphalt paving in UpTown Waterloo next week. This is an important milestone for the ION light rail transit (LRT) project.
The work will see the final layer of asphalt placed on Caroline, Allen and King, June 6-10, in four separate, 24-hour full road closures. A breakdown of the areas impacted each day is included below.
During this work, GrandLinq crews plan to place...

Read More...

Posted Thursday, May 25, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that they require a four-day closure of Columbia for final asphalt paving.
 
The full closure of Columbia, between Phillip and Hagey, will begin on or about Monday, May 29 and continue through Thursday, June 1. The work will see GrandLinq crews place the final layer of asphalt at the Columbia light rail transit crossing. The detour during this time will be Phillip-University-Westmount-Columbia.
...

Read More...