Posted Friday, November 03, 2017

Waterloo Region –  The Region of Waterloo is continuing public consultation on Stage 2 ION, light rail transit (LRT) from Kitchener to Cambridge.
At the last round of Public Consultation Centres (PCCs), a preliminary preferred route was presented for public feedback. During and after the last PCC, the Region received many comments from the public, including a number of suggested alternative routes. The Region will be further considering localized route alternatives...

Read More...

Posted Thursday, September 07, 2017

Waterloo Region – On Saturday, September 16, residents will have an opportunity to tour the ION Operations, Maintenance and Storage Facility (OMSF) as part of this year’s Doors Open Waterloo Region event. The Community Open House will take place from 10 a.m. to 5 p.m. at 518 Dutton Drive in Waterloo.
The OMSF is the operational hub of the ION light rail transit (LRT) system. This facility houses the Central Control Facility for ION and is where the ION trains...

Read More...

Posted Monday, June 12, 2017

Waterloo Region – GrandLinq has informed the Region that final asphalt paving operations on Caroline (Erb to Allen) and Allen (Caroline to King) in UpTown Waterloo have been postponed. The work, which was set to start yesterday (June 11), will be re-scheduled at a later date.
 
Final asphalt paving is postponed due to anomalies found on Saturday (June 10) during final testing related to cathodic protection. Cathodic protection significantly reduces rusting...

Read More...

Posted Thursday, June 08, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that they have re-scheduled final asphalt paving operations on Caroline and Allen in UpTown Waterloo, June 11-13. The work, which was originally scheduled for June 6-7, was postponed earlier this week due to weather. 
 
To minimize the impact on area businesses and residents, the work will be completed at night (7 p.m. to 7 a.m.), with access reinstated during the day. A full closure of...

Read More...

Posted Tuesday, June 06, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that due to the rain expected today, they will need to make adjustments to their final asphalt paving schedule in UpTown Waterloo.
 
The weather delay means that final asphalt paving on Caroline (Erb to Allen) and Allen (Caroline to King) originally scheduled to take place today (June 6) and Wednesday (June 7) will not occur this week. A new schedule for this work will be announced once arrangements...

Read More...