Final asphalt paving on Caroline and Allen in UpTown Waterloo postponed

Posted on Tuesday June 06, 2017

Waterloo Region – GrandLinq has advised the Region of Waterloo that due to the rain expected today, they will need to make adjustments to their final asphalt paving schedule in UpTown Waterloo.

 

The weather delay means that final asphalt paving on Caroline (Erb to Allen) and Allen (Caroline to King) originally scheduled to take place today (June 6) and Wednesday (June 7) will not occur this week. A new schedule for this work will be announced once arrangements have been made with area businesses regarding access and deliveries.

 

Final asphalt paving on King (Allen to the light rail transit crossing) and King (Allen to Union) is expected to proceed later this week.

 

During final asphalt paving operations, GrandLinq requires a full road closure for 24 hours. Crews are expected to pave the road during the day and stripe the road at night. All work is subject to construction constraints and weather conditions. Final asphalt paving can not take place in wet or humid conditions.

Revised UpTown Waterloo Final Asphalt Paving Schedule

 

Postponed – Caroline (Erb to Allen)

  • Full road closure, beginning at 7 a.m. for 24 hours
  • Caroline, from Erb to Allen
    • Work does not include the Caroline/Erb intersection
    • Intersections impacted: Father David Bauer/Caroline; Willis Way/Caroline; Alexandra/Caroline; William/Caroline; Fullerton/Caroline; Norman/Caroline; Freemont/Caroline

 

Postponed – Allen (Caroline to King)

  • Full road closure, beginning at 7 a.m. for 24 hours
  • Allen, from Caroline to King
    • Intersections impacted: Caroline/Allen
    • On-street parking on Allen will not be available during this time

 

Thursday, June 8 – King (Allen to the LRT crossing)

  • Full road closure, beginning at 7 a.m. for 24 hours
  • King, from North of Allen to the LRT crossing/railway tracks near the public square
    • Intersections impacted: George/King, Kuntz Lane/King, William/King, Willis Way/King
    • On-street parking on King will not be available during this time

 

Friday, June 9 – King (Allen to Union)

  • Full road closure, beginning at 7 a.m. for 24 hours
  • King, from Allen to Union
    • Work does not include the Union/King intersection
    • Intersections impacted: Allen/King, John/King
    • On-street parking on King will not be available during this time

For the latest ION construction information, visit www.rideION.ca or contact the toll-free GrandLinq hotline at 1-844-625-1010.

-30-

For more information, please contact:

Avril Fisken, Manager, GrandLinq Communications and Community Relations, 519-546-8454 or avril.fisken@aecom.com

 

Kimberly Newhouse, ION Manager of Community Relations, 519-575-4757 ext. 3461 or knewhouse@regionofwaterloo.ca